郑州市金桥路(桂圆路-香山路)等4条道路工程施工 第四标段 湖西路 投标文件技术标部分3-110Add:郑州市桐柏路43号科技大厦八楼 Tel(Fax):0371-63379636 63379619 Http:目 录第一章 总则··············································3-4一、编制说明············································3-4二、编制依据············································3-4第二章 工程概况··········································3-6一、工程简介············································3-6二、道路工程············································3-6三、排水工程············································3-9四、施工注意事项·········································3-10五、工期···············································3-11六、质量目标···········································3-11七、安全目标···········································3-12八、工程特点···········································3-12第三章 施工方案与技术措施·······························3-13一、施工方案···········································3-13(一)施工原则·······································3-13(二)施工计划及施工方案安排·························3-13二、施工技术措施·······································3-13(一)污水工程·······································3-13(二)雨水工程·······································3-19(三)道路工程·······································3-24第四章 质量管理体系与措施·······························3-44一、质量保证措施·······································3-44二、施工准备阶段质量控制································3-45三、施工阶段的质量控制··································3-46四、竣工验收阶段质量控制·······························3-47五、工程质量控制的实验方法·······························3-47六、竣工资料的整理及评定·······························3-47第五章 安全管理体系与措施·······························3-49一、建立安全生产保证体系·······························3-49二、安全生产目标·······································3-49三、交通疏导安全措施···································3-49四、确保安全生产的技术组织措施·························3-50五、应急组织及处理突发事件的措施·······················3-52第六章 文明及环保管理体系与措施·························3-55一、文明施工管理体系与措施·······························3-55二、环境保护管理体系与措施·····························3-57第七章 工程进度计划与措施·······························3-60一、施工原则···········································3-60二、工程施工计划·······································3-60三、施工进度计划图·····································3-60四、确保工期的技术组织措施·····························3-61五、施工准备工作·······································3-63第八章 施工期间的保通措施································3-66第九章 配合措施·········································3-67第十章 资源配备计划·····································3-69一、劳动力配备计划·····································3-69二、主要施工机械及仪器配备计划··························3-70三、材料配备计划·······································3-71第十一章 项目管理班子的配备·······························3-72一、项目管理机构组成···································3-72二、明确项目部各职人员职责·······························3-73第十二章 施工总平面图··································3-78第十三章 质量通病的防治措施······························3-80第十四章 冬、雨季施工措施·································3-92一、冬季施工措施·······································3-92二、雨季施工措·施········································3-93第十五章 按报价完成工程建设的技术和管理措施·············3-97一、确保按报价完成工程建设的技术措施···················3-97二、确保按报价完成工程建设的管理措施···················3-97附表一 拟投入的主要施工设备表···························3-99附表二 拟配备的试验和检测仪器设备表·····················3-101附表三 劳动力计划表····································3-102附表四 施工进度表······································3-103附表五 施工总平面图····································3-104附表六 临时用地表······································3-105施工组织设计第一章 总则一、编制说明1XX公司经过认真研究招标文件、设计图纸,仔细考察工程现场,对工程所处的位置进行综合研究,结XX公司多年的施工经验和目前的施工技术,组织编制了本施工组织设计。
2、在本工程组织设计编制中,充分考虑了各关键工序和重点工序及相互间的衔接与协调的可行性,及其相应的施工技术方案和工艺操作方法,本工程现场的地质条件、地上地下管线和交通情况可能对本工程产生影响,都作了充分的估计和准备3、如XX公司中标,我们将在施工的全过程密切配合建设及监理单位的工作,并与周边单位、村庄、社区群众协调好关系,创造良好的施工环境,确保本工程施工合同的全面履行4、本施工组织设计只对本次招标范围第4标段湖西路(郑上路~风茂街)污水、雨水、道路工程有效二、编制依据1、_天一招标咨询XX公司《XX市金桥路(桂园路~香山路)等4条道路工程施工招标文件》,编号ZZTY-20__-027;2、XX市金桥路(桂圆路~香山路)等4条道路工程施工招标答疑;3、XX市金桥路(桂圆路~香山路)等4条道路工程施工招标答疑(二);4、XX第一勘察设计院集团XX公司:XX市湖西路(郑上路~风茂街)南段道路工程施工图设计(全一册);5、《给水排水管道工程施工及验收规范》 GB50268-2008;6、《砌体工程施工质量验收规范》 GB50203-2002;7、《公路路面基层施工技术规范》 TJ034-2000;8、《公路沥青路面施工技术规范》 JTG F40-2004;9、《沥青路面施工及验收规范》 GB 5009-96;10、《城镇道路工程施工与质量验收规范》 CJJ1-2008;11、XX市建设委员会郑建[2007]98号文《关于促进新型墙体材料发展全面禁用粘土类墙体材料的通知》;12、_恒兴工程建设XX公司《程序文件》及《管理手册》。
第二章 工程概况一、工程简介XX市金桥路(桂圆路~香山路)等4条道路工程,包含道路、雨水、污水工程本施工组织设计为本次招标范围的第4标段—湖西路(郑上路~风茂街)道路、雨水、污水工程二、道路工程1、XX市湖西路(郑上路~风茂街)位于XX市中原区西流湖以西,规划为南北XX市次干路,道路红线宽30m,路段全长1050m2、道路平面设计湖西路南段共设3个曲线,最小曲线半径为200m,交叉口分别进行规范化交通控制设计3、道路纵断面设计根据连接郑上路起点实测高程及规划路交叉口的规划高程进行控制最大坡度为2.0%,最小纵坡度0.45%4、道路横断面设计湖西路南段横断面布置形式为:6m(人行道)+18m(混行车道)+6m(人行道)道路设计标高为道路路面中心线标高5、路基、路面设计⑴路基横断面布置6m(人行道)+18m(混行车道)+6m(人行道)⑵一般路基工程①边坡设计局部有条件放坡的填方路段,边坡坡度为1:1.5;挖方路段,边坡坡率为1:1~1:1.5②填料、压实度路基填料均匀、密实,优先选用级配较好的砾类石、砂类石等粗粒土;挡土墙背优先选用渗水性良好的填料填方路基分层铺筑,均匀压实,并严格控制分层厚度,注意不同填料的填筑顺序。
土质路基压实度(重型)符合以下要求:一般路堤,路面底面以下:0~80cm不小于95%,大于80cm不小于93%零填方及路堑路面底面以下0~30cm的路床不小于95%③路基边坡防护工程AK0+720~AK0+770段填方地段右侧边坡设扶壁式路肩挡土墙收坡,墙顶设防护栏杆挡土墙型采用悬臂式路肩挡土墙,挡土墙墙身、底板均采用C30混凝土现浇受力钢筋为Ⅱ级钢筋,分布筋为Ⅰ级钢筋,钢筋最小保护层厚度不小于3.0cm为控制沉降及增加承载力,挡土墙基底设1.0m碎石垫层AK0+200~AK0+330段右侧边坡设骨架护坡防护,骨架内种植红叶石楠⑶路面工程①路面类型混行车道采用沥青混凝土路面,人行道采用混凝土透水砖 ②路拱形式混行车道采用1.5%的直线型双面横坡,人行道采用1.5%的直线型单向横坡③路面结构混行车道4cm厚细粒式沥青混凝土(AC-13C)6cm厚中粒式沥青混凝土(AC-20C)0.6cm稀浆封层36cm厚水泥粉煤灰碎石(3.5:12:84.5)18cm厚水泥石灰稳定土(4:12:84)面层间设粘层油(0.3kg/㎡)人行道6cm厚C30混凝土预制块2cm厚M7.5水泥砂浆18cm厚水泥粉煤灰碎石(3.5:12:84.5)水泥粉煤灰碎石的7天无侧限抗压强度不小于3.0Mpa,水泥石灰土底基层7天无侧限抗压强度不小于1.5Mpa。
④无障碍盲道设计根据施工图设计,距树池0.5~0.8m处设置盲道,行进盲道的起终点及拐弯处设圆点形的提示盲道,其长度大于行进盲道的宽度,人行道中有台阶、坡道和障碍物是,在相距0.25~0.5米处设提示盲道;人行道在交叉路口、街坊路口、单位出口、广场入口、人行横道等路口均设缘石坡道⑤侧平石、边石、树池设计采用C30混凝土侧石,规格为100cm×35cm×25cm,外露高度22cm,外露表面光亮采用C30混凝土平石,规格为50cm×50cm×10cm,露高度22cm,外露表面光亮采用C30混凝土边石,规格为50cm×15cm×8cm,外露端为圆头,表面光亮人行道上种植行道树,行道树间距7米,树池尺寸为1.5m×1.5m,采用预制混凝土边石围边⑥路基路面排水路面采用集中排水方式路面水通过每隔一定距离设置在人行道或机动车道侧的雨水口汇集,并通XX市地下排水管网集中排除6、道路工程施工注意事项⑴路基施工前做好排水工作⑵路基范围内的浮土及垃圾等先清除后,再进行路基工程的施工⑶填筑路基是按层水平填筑,并按要求的压实度进行严格空控制⑷开挖工程施工时,注意地下管线的位置,以免造成事故⑸边坡开挖后,如有松动岩石、土体,现行清理,然后施工。
⑹注意边坡、基坑开挖后及时防护,以免石膏土遇水后溶解、膨胀,破坏边坡稳定性和产生基床病害⑺严格按照设计要求尺寸进行调查,确保附近的输油管道、光缆、电缆等设施安全对施工中新发现的以上设施,马上停止施工,并及时上报有关部门⑻现场实际情况若与设计不符,尽快与设计人员联系,以便及时予以处理7、主要工程量详见预算书三、排水工程1、排水相关规划雨水:风茂街~北岗路,规划d600~d1000雨水管向北排放,在风茂街路口处向东排入西流湖北岗路~郑上路,规划d500、d700雨水管向顺道路坡度排放,在路段低点处向东排入西流湖污水:郑上路~风茂街,规划d500向北排放,最终进入铁西路现状d1500污水干管2、排水工程设计原则⑴解决湖西路工程范围及周边雨、污水的排放⑵根据所属地区的排水体制,采用雨、污水分流体制⑶雨水泄水范围:规划雨水系统的路段按规划分系统划分泄水范围⑷污水服务范围:按系统划分服务范围3、雨、污水工程⑴本次雨水、污水管材采用Ⅱ级钢筋混凝土管承插口管D500及以下采用150°砂石基础,D500以上采用120°砼基础,管道接口采用承插式橡胶圈接口⑵管道沿线附属构筑物主要为雨水口及检查井,雨水口采用偏沟式、联合式雨水口等形式。
⑶本次雨、污水工程,采用开槽法施工,不考虑降水沟槽开挖及回填严格按《给水排水管道工程施工及验收规范》(GB50268-2008)的要求执行4、管材及施工排水管道施工:按开槽埋管考虑管材:采用承插式Ⅱ级钢筋混凝土管5、排水工程施工注意事项及质量验收要求⑴施工时对原有地下管线资料进行详细调查,必要时开挖掘洞实探,防止损坏原有管道、管线⑵对已建管道及附属构筑物等与本工程衔接部分的平面位置及高程,施工前校测⑶管道安装完成后在回填前采用灌水法进行严密性试验,试验按照《给水排水管道工程施工及验收规范》(GB50268-2008)执行⑷施工中严格执行相关规程、规范⑸施工中遇有如与设计不符时及时与设计人员联系解决,以便及时处理6、主要工程量详见预算书四、施工注意事项1、施工前查对、复核导线点和水准点等桩志和有关测量资料,发现桩志不足、不妥、位置移动或精度与要求不符,均进行补测,加固,并及时与设计单位取得联系2、施工前复核已有道路高程及控制点坐标,并注意与其相交道路的衔接3、施工中若发现未预计情况,及时与监理单位、建设单位、设计单位联系,由建设单位或监理单位主持,共同协商解决4、路基施工前注意做好排水、降水工作,同时做好临时排水工程,以防止路基浸水,影响路基施工质量。
5、路基范围内的垃圾等清除后,在进行路基工程施工6、路基填筑时,基底达到相应的密实度,避免出现“弹簧土”,如属低填路基时,更注意施工质量,并按有关规范要求的密实度进行严格控制7、为确保土基达到要求的回弹模量,严格按有关规程要求进行碾压,且避免雨季施工严格控制土基回弹模量,以避免以后可能出现的路面隐患8、基层及面层的路面的施工严格按《公路沥青路面施工技术规范》JTG F40-2004、《公路路面基层施工技术规范》TJ034-2000进行9、加强施工安全防护措施,确保施工人员安全10、施工前对施工现场地下管线、光缆、电缆设施进行调查,发现应停止施工及时上报11、若实际施工与设计有出入时,及时与设计人员联系,其余未尽事宜,按相关施工规范办理五、工期招标文件要求工期为120日历天为使本工程早日建成并投入使用,尽早给XX市民带来交通便利、保证业主的投资早见成效,根XX公司的施工能力、施工经验及机械设备情况,经方案对比优化,确定本工程施工总工期为120日历天六、质量目标招标文件要求达到合格质量等级XX公司承诺本工程的质量目标为合格工程七、安全目标招标文件要求安全要达到不发生任何人员伤亡事故XX公司承诺本工程的安全管理目标:施工中做到不发生任何人员伤亡事故,因本岗位造成的职业伤害为零,职业发病率为零。
八、工程特点 1、本工程施工任务量较大,现场情况复杂需要统筹计划、合理安排 2、本工程在夏季开工,作好开工前的劳动力进场和保证施工期间的劳力充足工作对保质保量完成施工任务尤为重要3、本工程施工材料使用量较大,因此,在施工过程中应根据施工进度及现场情况及时作好各种材料的采购和调运工作以满足施工需要4、本工程现场土方量大,需要大量清运;对于地下垃圾要换填素土;工程沿线有现状鱼塘,需要清淤处理以上因素对工程的工期,质量有很大影响,给工程的组织管理工作提出了较高的要求第三章 施工方案与技术措施一、施工方案(一)施工原则根据本工程施工任务重、工期短等特点,采取分段施工,各个施工段自下而上,先施工污水、再施工雨水、最后施工道路的顺序进行,各个施工段的各个工序衔接紧密、流水作业做到保质量、保安全、保工期,确保目标实现二)施工计划及施工方案安排工程施工由项目经理统一指挥,项目部管理人员各司其职、密切配合,充分调动全体参加施工人员的主观能动性,确保施工按计划、方案实施1、工程施工计划及施工安排计划将本标段划分为两大施工段,由两个施工队承担施工任务,施工段之间进行平行施工流水作业具体任务分工:第一流水施工段:A:0+000~0+515第二流水施工段:B:0+515~1+0502、施工方案:先干污水,再干雨水、道路等严格按照工程进度计划制定的时间和施工工序安排施工,各工序间以及各施工段之间紧密配合,互相衔接,确保工程进度控制计划顺利实施,做到保质量、保安全、保工期,确保既定工程计划实现。
详见湖西路工程施工进度表二、施工技术措施(一)污水工程1、工艺流程见下图: 开挖沟槽基础施工铺设管道砌筑检查井闭水试验、回填土污水管道施工工艺流程框图随挖随测现场监理检查验收测量放样监理工程师验收认可施工方案审批 2、施工方法⑴测量放线施工前测量:对给定的坐标、高程数据进行复核,复核无误后根据施工现场地形特点建立首级平面、高程控制点,在此基础上对施工沿线坐标、高程加密,形成完整的控制体系认真审核图纸,发现有关问题及时与设计、业主、监理联系,协商解决利用计算机技术做好前期测量数据准备,做好测量资料管理,保证测量数据准确、规范开工前进行现况地型纵横断面复测,取得原始测量成果,与施工图结合施工选用年检合格的:全站仪、经纬仪、水准仪等,仪器必须有当年的检验合格证,随时复核坐标、水准点,调整、修改加密控制点施工中测量:施工中进行水准点复核,对临时水准点进行闭合,闭合差XX市政测量规范要求对导线进行闭合,根据边长值,测得的角中误差,距中误差符合相应精度要求填写高程与导线复核记录,上报监理复测确认管道施工设牢固的坡度板或高程桩,使管道中心、高程符合设计要求道路工程利用牢固建筑物或稳固高程桩控制道路高程中心。
对桩位采取砌墩保护,并随时复测校核⑵管道沟槽开挖①管道沟槽开挖前,必须搞清楚开挖段的地下情况,可根据设计图及有关资料或调查结果,采用挖探坑的方法查明情况;对施工管道与已有管道等构筑物连接的,应对其位置和高程进行复核,发现不符及时通知设计部门予以解决;开挖前将开挖断面、堆土位置和高度、地下构筑物情况、安全要求、技术要点等向挖掘机司机及有关人员进行详细交底②管道沟槽开挖采用机械开挖人工配合,按管线设计位置,沟槽开挖由专人指挥随挖随测,依图纸设计及施工规范进行放坡,堆土坡脚距开挖沟槽边大于1m;开挖时应在设计槽底高程以上保留厚20cm左右不挖,采用人工随时清挖(必要时机械配合)③管道沟槽开挖时各级质安人员加强巡视,一旦发现质量、安全问题或隐患应随时停止、并进行处理或上报沟槽开挖以每井段为一流水作业段,完成一段,回填一段④基底处理 管道基底之下的树根、淤泥、腐殖土、草皮以及垃圾全部清理干净,清除至原状土,并换填素土、分层夯实有地下水时加强降水措施,保证降水效果;管道基础下软基厚度大于80cm时,将软基清除80cm后,先用砖渣稳固地基,再铺垫水泥石灰土两层(厚30cm),其上再进行管道基础正常敷设;若软基清除80cm后挖出淤泥,则首先进行抛石挤淤,稳固地基后再铺筑砖渣及30cm厚水泥石灰土垫层,最后进行管道基础正常敷设。
软基处理措施视具体情况现场商定并进行试验,根据处理效果确定推广或重新拟定处理方案3)管道施工①基础管道基础采用天然级配砂石基础管道基础支承角应依基础地质条件、地下水位、管径及埋深等条件由设计计算确定,本工程基础支撑角为150°管道基础应按设计要求铺设,厚度不得小于设计规定基础各部位的回填压实度应符合规定②管道安装排管前要先对槽底高程复核,复核无误后铺设砂石,保证砂砾厚度,并在井位架设龙门杆以控制中线,龙门杆架设要牢固,不得有松动管节安装前对管材按产品标准逐支检查,不符合标准不得使用管道安装可采用人工安装槽深不大时可由人工抬管入槽,槽深大于3m或管径大于公称直径DN400mm时,可用非金属绳索溜管入槽,依次平稳地放在砂基础管位上严禁用金属绳索勾住两端管口或将管材自槽边翻滚抛入槽中承插口管安装,管道承口应放在检查井的进水方向,插口方向应放在检查井的出水方向,由低点向高点依次安装③接口接口前,应先检查橡胶圈(具体标准执行04S516附录三的相关规定)是否配套完好,确认橡胶圈安放位置及插口的插入深度接口时,先将承口的内壁清理干净,并在承口内壁及插口橡胶圈上涂润滑剂(首选硅油),然后将承插口端面的中心轴线对齐。
接口方法按下述程序进行:由2台0.5吨手板葫芦将管材拉动就位接口合拢时,管材两侧的手板葫芦应同步拉动,使橡胶密封圈正确就位,不扭曲、不脱落为防接口合拢时已排设管道轴线位置移动,需采用稳管措施具体方法可在编织袋内灌满黄砂,封口后压在已排设管道的顶部,其数量视管径大小而异管道接口后,应复核管道的高程和轴线使其符合要求接口完成后,回填至设计要求值高度4)检查井施工①井基础应与管线基础同时进行,并符合设计要求,管子排好后可开始砌井,砌井前管头要凿毛②砖在砌筑时砖要放平,砂浆饱满,砌筑缝要错开,特别要注意管头下部及管子周围必须砌筑密实,管头要凿毛检查井的流槽应在井壁砌到管顶以下即行砌筑,并应用砂浆分层压实抹光③井的各部位尺寸均应符合设计要求,踏步应按设计放平,上下对正,砂浆密实、砖要压紧,砂浆在凝固前,不得碰撞,更不允许受力,以免造成松动砖砌圆形检查井,应随时检测直径尺寸,当需收口时应按设计收进④砌筑检查井的井室内壁应按设计进行抹面,内壁抹面分层压实,井室外壁用砂浆抹面内外粉刷执行技术操作规范,砂浆要按配比拌合均匀,粉刷要求密实平整不得有空鼓现象,流槽应光滑圆顺⑤井砌好后及时安装井盖,检查井的井盖的型号符合设计要求,其高程符合设计要求。
⑥预留支管:预留管的管径、方向、标高符合设计要求,管与井壁衔接处应严密不得漏水⑦井外回填土:检查井砌筑边砌边回填周围水泥石灰土,每层厚不得超过20cm5)污水管道闭水试验污水管道施工完毕,根据规定需做闭水试验闭水试验前具备下列条件:管道的外观质量及“量测”检验均已合格管底与基础腋角部位回填密实,全部预留管洞应封堵不得漏水管道两端的管堵封堵严密、牢固砌筑缝水泥砂浆及砼达到设计强度要求闭水试验水头为上游管道内顶以上2m,先在管道预先充满水后,再按水头高度加水试压20min,待水位稳定后进行正式闭水试验,观测管道24h小时的渗漏量对于闭水试验达到要求的管段,可以进行回填,否则认真查明原因,及时处理经重新闭水试验合格后方可进行回填6)沟槽回填①管道沟槽回填排水管道工程的隐蔽工程验收合格后及时回填管沟,回填土分层铺土进行夯实,铺土厚度为20cm,用平板振动夯夯实,回填土按要求进行施工及验收,密实度要求按相应规范要求执行②沟槽回填应注意以下事项:沟槽回填顺序按沟槽排水方向由高向低分层进行沟槽内不得有积水支撑拆除与回填土的填筑高度配合进行,且在拆除后及时回填沟槽两侧同时回填夯实,以防管道位移井室等附属构筑物回填土四周同时进行。
分段回填时,相邻段的接茬形成台阶,每层台阶宽度不小于厚度两倍二)雨水工程1、工艺流程开挖沟槽垫层施工铺设管道、基础施工砌筑检查井回填土雨水管道施工工艺流程框图随挖随测现场监理检查验收测量放样监理工程师验收认可施工方案审批2、施工方法⑴测量放线施工前测量:对给定的坐标、高程数据进行复核,复核无误后根据施工现场地形特点建立首级平面、高程控制点,在此基础上对施工沿线坐标、高程加密,形成完整的控制体系认真审核图纸,发现有关问题及时与设计、业主、监理联系,协商解决利用计算机技术做好前期测量数据准备,做好测量资料管理,保证测量数据准确、规范开工前进行现况地型纵横断面复测,取得原始测量成果,与施工图结合施工选用年检合格的:全站仪、经纬仪、水准仪等,仪器必须有当年的检验合格证,随时复核坐标、水准点,调整、修改加密控制点施工中测量:施工中进行水准点复核,对临时水准点进行闭合,闭合差XX市政测量规范要求对导线进行闭合,根据边长值,测得的角中误差,距中误差符合相应精度要求填写高程与导线复核记录,上报监理复测确认管道施工设牢固的坡度板或高程桩,使管道中心、高程符合设计要求道路工程利用牢固建筑物或稳固高程桩控制道路高程中心。
对桩位采取砌墩保护,并随时复测校核2)管道沟槽开挖①管渠沟槽开挖前,必须搞清楚开挖段的地下情况,可根据设计图及有关资料或调查结果,采用挖探坑的方法查明情况;对施工管渠与已有管渠等构筑物连接的,对其位置和高程进行复核,发现不符及时通知设计部门予以解决;开挖前将开挖断面、堆土位置和高度、地下构筑物情况、安全要求、技术要点等向挖掘机司机及有关人员进行详细交底②管渠沟槽开挖采用机械开挖人工配合,按管线设计位置,沟槽开挖由专人指挥随挖随测,依图纸设计及施工规范进行放坡,堆土坡脚距开挖沟槽边大于1m;开挖时应在设计槽底高程以上保留厚20cm左右不挖,采用人工随时清挖(必要时机械配合)③管道沟槽开挖时各级质安人员应加强巡视,一旦发现质量、安全问题或隐患应随时停止、并进行处理或上报沟槽开挖以每井段为一流水作业段,完成一段,回填一段④基底处理 管道基底之下的树根、淤泥、腐殖土、草皮以及垃圾全部清理干净,清除至原状土,并换填素土、分层夯实有地下水时加强降水措施,保证降水效果;管道基础下软基厚度大于80cm时,将软基清除80cm后,先用砖渣稳固地基,再铺垫水泥石灰土两层(厚30cm),其上再进行管道基础正常敷设;若软基清除80cm后挖出淤泥,则首先进行抛石挤淤,稳固地基后再铺筑砖渣及30cm厚水泥石灰土垫层,最后进行管道基础正常敷设。
软基处理措施视具体情况现场商定并进行试验,根据处理效果确定推广或重新拟定处理方案3)管道施工①垫层A、砂石垫层:管道垫层采用天然级配砂石管道垫层应按设计要求铺设,厚度不得小于设计规定基础各部位的回填压实度应符合规定B、混凝土垫层:按设计要求确定检查井位置,放线、立钢模或木模,经模板安装验收合格后浇注基础砼砼采用商品砼,拌制好的砼运抵施工点后,用流槽将砼导入沟槽底部及时用振动棒将砼捣实,然后用平板振动器拖平,再人工抹平拉毛②管道铺设排管前要先对槽底高程复核,复核无误后铺设砂石,保证砂石厚度,并在井位架设龙门杆以控制中线,龙门杆架设要牢固,不得有松动管节安装前应对管材按产品标准逐支检查,不符合标准不得使用管道安装可采用人工安装槽深不大时可由人工抬管入槽,槽深大于3m或管径大于公称直径DN400mm时,可用非金属绳索溜管入槽,依次平稳地放在砂基础管位上严禁用金属绳索勾住两端管口或将管材自槽边翻滚抛入槽中承插口管安装,管道承口放在检查井的进水方向,插口方向放在检查井的出水方向,由低点向高点依次安装③接口处理接口前,先检查橡胶圈(具体标准执行04S516附录三的相关规定)是否配套完好,确认橡胶圈安放位置及插口的插入深度。
接口时,先将承口的内壁清理干净,并在承口内壁及插口橡胶圈上涂润滑剂(首选硅油),然后将承插口端面的中心轴线对齐接口方法按下述程序进行:由2台0.5吨手板葫芦将管材拉动就位接口合拢时,管材两侧的手板葫芦应同步拉动,使橡胶密封圈正确就位,不扭曲、不脱落为防接口合拢时已排设管道轴线位置移动,需采用稳管措施具体方法可在编织袋内灌满黄砂,封口后压在已排设管道的顶部,其数量视管径大小而异管道接口后,应复核管道的高程和轴线使其符合要求 ④管道基础A、砂石基础:采用天然级配砂石基础管道基础支承角依基础地质条件、地下水位、管径及埋深等条件由设计计算确定管道基础按设计要求铺设,厚度不得小于设计规定基础各部位的回填压实度应符合规定B、混凝土基础:管节安装完成后,经检验中心线、高程合格后,立即支设钢模板模板支好后清除模板中的尘渣、异物,核实模板尺寸管座浇筑前先将管座平基冲净浇注时先从一侧灌注砼,当对侧的砼与灌注一侧砼高度相同时,两侧再同时浇筑,并保持两侧砼高度一致浇筑砼时,留置砼抗压强度试块,按每工作班组不应少于一组,每组3块,按《砼结构工程施工及验收规范》GB50204—2002进行强度评定4)检查井施工砖砌井:井基础与管线基础同时进行,并符合设计要求。
管子排好后开始砌井,砌井前管头要凿毛砖在砌筑时砖放平,砂浆饱满,砌筑缝错开,特别要注意管头下部及管子周围必须砌筑密实,管头要凿毛检查井的流槽应在井壁砌到管顶以下即行砌筑,并用砂浆分层压实抹光井的各部位尺寸均符合设计要求,踏步按设计放平,上下对正,砂浆密实、砖要压紧,砂浆在凝固前,不得碰撞,更不允许受力,以免造成松动砖砌圆形检查井,随时检测直径尺寸砌筑检查井的井室内壁应按设计进行抹面,内壁抹面分层压实,井室外壁用砂浆抹面内外粉刷执行技术操作规范,砂浆要按配比拌合均匀,粉刷要求密实平整不得有空鼓现象,流槽光滑圆顺井砌好后及时安装盖板及井盖,检查井的井盖的型号符合设计要求,其高程符合设计要求预留支管:预留管的管径、方向、标高符合设计要求,管与井壁衔接处应严密不得漏水 (5)沟槽回填①管道沟槽回填排水管渠工程的隐蔽工程验收合格后需及时回填管沟,回填土分层铺土进行夯实,铺土厚度为20cm,用平板振动夯夯实,回填土按回填土的要求进行施工及验收,管沟回填采用分层夯填的方法,夯实机具采用电夯,密实度控制按设计图纸和现行规范要求执行②沟槽回填注意以下事项沟槽回填顺序按沟槽排水方向由高向低分层进行沟槽内不得有积水。
井室等附属构筑物回填土四周同时进行 (三)道路工程1、施工顺序路基土方工程→路基挡土墙、护坡→路床成型→水泥石灰土底基层→水泥粉煤灰碎石基层→侧、平石→沥青砼路面→人行道板铺装2、施工方法(1)路基土方工程:①填方路段施工: A、污水、雨水工程完工后,恢复道路中心桩及坡脚桩为了保证压实宽度不得小于设计宽度,填土宽度每侧应宽于填层设计宽度50cm最后削坡B、填土前应将原地面的草根、树根和其他易腐物清除干净水坑、树坑等低洼处应先分层填土夯实,将原地面大致找平,经碾压处理达到规定的压实度C、填土所需的土严禁使用过湿或含有机物过多的土及垃圾土,土中的大土块应打碎或取出,最大土粒径不得大于5cm,土的含水量在碾压时应接近最佳含水量D、在路基总宽度内采用分层方法填筑,每层虚铺厚度按30cm进行控制,采取自卸汽车运土、推土机平整填土、压路机碾压成型的施工方法应按照横断面全宽逐层向上填筑,每填一层,经过压实符合规定要求之后再填一层E、碾压工作应自边向中进行,宜先轻后重至表面无显著轮迹、达到要求压实度为止碾压时碾轮外侧距填土外缘不得小于50cm,以防发生溜坡事故F、为了防止各施工层表面有积水,其表面应自道路中心线向两侧做2%的坡度确保在施工过程中能及时将雨水排走。
G、填土到最高层后,应恢复并仔细复核道路中线、路基边线及纵横断面,按要求进行路基整修、边坡削坡修整,使之符合设计要求②挖方路段施工:A、污水、雨水工程完工后,恢复道路中心桩及坡脚桩为了保证压实宽度不得小于设计宽度,挖土宽度每侧应宽于道路设计边线宽度50cmB、大面积采用挖掘机开挖挖除的建筑垃圾、生活垃圾当时用自卸车拉走,挖出的干净素土集中堆放,留作路床、灰土基层使用C、挖方深度以设计路床标高以上20cm为标准;严禁超挖⑵挡土墙施工①工艺流程:测量放线 、基坑开挖 →钢筋加工→ 支设脚手架→支设模板→浇筑混凝土→土方回填→护栏安装②施工方法A、基础开挖a、测量放线、定点定位、打入标识桩、测量必须复测、符合精度要求后,打入标桩,做好防护,地面撒上白灰线b、挖掘机挖土,汽车运土,靠近既有路堤一侧开挖基础时,要按1:0.5放坡,必要时打入钢轨桩,以防路基溜坍,基底不得超挖,一旦超挖不得用土回填c、人工清理基底覆土,基底要平整,不得凹凸不平d、平整基底后,用夯机夯实,经监理、设计、建设单位验槽后,立即回填碎石e、碎石垫层厚度0.3m,平整夯实后,进行钢筋绑扎B、钢筋加工a、钢筋按设计长度量测后,用画石笔划印,然后用钢筋切断机切断,按规格分堆积如山码放,做好标识、底部放木方与地面隔离。
b、钢筋按设计尺寸弯制,弯曲的钢筋要平顺、光滑、无扭曲、翅曲c、钢筋焊接采用闪光对焊或双面焊缝搭接焊d、钢筋骨架组装采用焊接、绑扎相结合的方法注意事项:Ⅰ、钢筋接头在受拉区、同一截面上不得超过25﹪,同一根钢筋在同一截面上不得有两头以上接头Ⅱ、同品牌钢筋不能以细代粗,可以以粗代细Ⅲ、闪光对焊钢筋接头时,必须先对焊并没有作拉伸试验Ⅳ、钢筋弯制需在常温下进行,不得加热弯制Ⅴ、钢筋骨架与模板间垫脚石块要呈梅花形布置Ⅵ、绑制完的钢筋骨架要平顺,位置要正确Ⅶ、钢筋骨架安置后,不得在其上行走,堆放料具C、支设脚手架a、搭设脚手架采用钢管,用十字扣联接b、脚手架立柱要保持垂直,不应倾斜,置于坚实地基上垂直误差不大于1%c、纵向的水平钢管的垂直间距不大于1.8m,承重的做纵向水平杆必须支承于横杆上,禁用不合格材料d、外排架必须保持高出工作面1.2m,临时通道两侧设防护栏杆e、脚手架两端转角处,每隔6-7根立柱应设剪刀撑,剪刀撑与地面的夹角不大于60°f、脚手架搭设不留有空隙和探头板,铺板应用铁丝绑扎牢固,坡度不得大于1:2,防滑条间距以30cm为宜,不做立柱和横杆注意事项:Ⅰ、搭拆脚手架的操作人员,必须戴安全帽。
临空危险作业必须配带安全带,严禁穿拖鞋、赤脚或感硬底鞋上架操作,严禁酒后作业Ⅱ、拆卸架前要检查,架上是否有杂物,电线水管等临时设施,必须先清除干净后拆除Ⅲ、拆架时,就应先上后下,不准上下同时作业D、支设模板a、模板修理、表面除锈、涂油b、模板间隙用密封条封闭c、模板间的拉片,卡扣安装要保证要保证模板在混凝土侧压下不变形d、模板要安设牢固,上部模板安装时,要用滑轮提开e、墙体模在一定位置预留洞口,混凝土灌注后,要及时封口f、支模过程中,如需中途停止,应将支撑,搭头,柱头板等钉牢g、拆除模板一般用长撬棍,防止整块模板掉下,以免伤人h、拆除模板从上至下,不得上、下同时作业注意事项:Ⅰ、施工人员戴安全帽、安全带,不得赤脚或穿拖鞋Ⅱ、得从高处抛掷模板、卡扣、联结零件Ⅲ、拆模作业区内,严禁闲杂人员逗留E、浇筑混凝土a、混凝土采用C30商品混凝土,用专用混凝土搅拌运输车b、混凝土采用泵送入模的方式、分层浇筑,每层浇筑高度不大于0.6m c、混凝土采用插入式振捣棒振捣,每个振捣棒配2人,计划用3台振捣棒d、在地板混凝土凝固后,在进行立臂混凝土浇筑,立臂与底板相接处,将底板顶部地混凝土凿毛,但不留残渣e、墙体浇注、施工缝设在不同高度。
f、振捣时,必须保证混凝土震捣密实,不得出现蜂窝、麻面g、随时检查钢筋骨架,确保保护层厚度,确保不露筋h、混凝土入模时的速度要严格控制,避免胀模i、混凝土浇注过程中要随时检查、模板有无变形、离缝现象,一旦出现问题,要立即停止浇注,加固模板j、混凝土浇注要连续,中间不得停顿,停歇时间超过1.5小时要做施工缝处理k、随时检查混凝土的坍落度F、土方回填a、挡土墙混凝土强度达到设计强度的75%后,回填土方基b、靠近墙背1.5m范围内用小型振捣器分层夯实,每层厚度不大于20cm,其它范围内用压路机碾压密实c、墙背后设30cm厚砂砾石反滤层,最低排泄水孔的下部设黏土隔水层沿墙长和墙高按上下左右交错布置泄水孔,间隔2-3米,最底排泄水孔位于墙前地面线以上20cm处泄水孔采用直径5cm的PVC管,进口采用反滤土工布包扎G、护栏制作安装a、基础处理应符合下列规定安装防护栏杆立杆的杯形槽部位,基础混凝土不得有酥松现象,并且安装标高应符合设计要求,凹凸不平处必须剔除或修补平整,过凹处及基层蜂窝麻面严重处,不得用水泥砂浆修补,应用高强混凝土进行修补,并待有一定强度后,方可进行栏杆安装b、栏杆安装栏杆的施工采用厂内下料制作,栏杆散件运至施工现场安装的施工方法。
下料:栏杆下料应严格按图纸尺寸下料,切割面要光滑,不允许有毛刺,切割边缘要打磨平滑 铣槽:栏杆扶手与立柱的开槽尺寸须准确 打磨:栏杆需进行抛光处理,抛光处理要仔细,抛光材料的选用不低于原材料抛光颗粒细度的10-15% 运输:厂内下料完成后,用塑料膜包装好,运至施工现场,要求运输时用木板垫好,绑牢c、栏杆安装操作要点:Ⅰ、按设计及安装要求正确弹出栏杆立杆安装间距位置和中心线栏杆立杆安装应按要求及施工墨线进行平台两端立杆应先安装(立柱放好后,杯形槽内用细粒石混凝土浇筑)两端立杆安装完毕后,拉通线用同样方法安装其余立杆立杆安装必须牢固,不得松动立杆焊接接部位,在安装完后,应进行防腐防锈处理,并且不得外露,应在根部安装装饰罩或盖Ⅱ、栏杆安装时,要求立柱要垂直,间距准确现场安装完毕,用软布将栏杆上的污物擦除干净,打磨除锈后涂刷防锈漆两道 d、质量要求 Ⅰ、栏杆选用的材料必须符合图纸和规范要求,具有出厂合格证及原始资料 Ⅱ、栏杆的连接要牢固,稳妥,不得晃动,强度要符合焊接要求 Ⅲ、栏杆立柱要垂直,垂直偏差不大于2mm,栏杆立柱与扶手连接处的缝隙不大于0.2mm Ⅳ、栏杆接口处的焊接,应打磨光滑,与原材无明显差异。
焊接施工中焊条应与母材材质相同,安装时将立杆临时固定,经标高、垂直校正后,施焊牢固焊接时(特别是冬期施工),应掌握好焊接电流、电压及焊接温度,以防电流过大或过小及电压不稳,影响焊接质量和美观焊接质量应符合有关规定的标准,焊缝宽度、深浅要一致,表面应呈鱼鳞状,扶手接头焊缝应严密,焊缝应无明显手感偏差Ⅴ、栏杆表面要清洁,不允许有划痕3)护坡施工①施工工艺施工前准备→测量放线→边坡清刷→砌筑骨架护坡→检查验收③施工工艺方法A、施工准备a、材料浆砌防护的材料主要是砂、片石、水泥材料进场前需各种原材料的品质进行试验,合格后方可进场,在材料进场后还要对砼的原材料进行抽检,其各项指标均要符合设计的要求试验室提供施工的砂浆的配合比b、施工场地对边坡清理完毕后,合理组织施工,原材料的堆放、电力、水源的问题,特别要注意施工顺序及施工组织B、路堤分段成型后,安排人工按照设计边坡坡率挂线清刷修整边坡、拍实,使坡面平整C、边坡清理完成后按设计型式、尺寸对骨架挂线放样,确定伸缩缝和浆砌踏步的具体位置后再进行基坑沟槽的开挖D、基坑开挖的断面尺寸符合设计要求,基坑开挖完成并报监理工程师检查合格后,方可进行基础圬工的施工。
E、因为基坑是土质基坑,砌筑骨架基础时直接采用座浆法砌筑F、砌筑骨架从衔接处开始,自下而上砌筑,两骨架衔接处应处于同一高度骨架应与坡面密贴,骨架流水面应与草坡表面平顺骨架基础与下部侧沟平台浆砌片石或浆砌片石水沟连接时,应整体砌筑,灰浆饱满不留缝隙G、为便利养护,于适当位置设阶梯形踏步踏步和路堤坡面排水槽设在主骨架处 (4)路床施工路床施工前对施工现场的土质做重型击实试验,并将拟进场的施工机械进行合理组合,报监理工程师审批;而后做试验段,进行进场设备及各种填料的试验,以确定为达到质量要求的进场填料的类型和机械设备的最佳配合,各类压实设备的各自碾压遍数下的压实厚度、松铺系数等,并以此作为在现场施工过程中的控制依据路床施工工艺流程:见下图 填方路段挖方路段施工准备清除腐殖土及杂物倒运土方分层摊铺机械碾压密实人工平整高程检测路床施工工艺流程框图测量放样测量放样、人工清扫压实度检测路床成型进入下道施工工序机械开挖人工配合机械平整高程控制含水量控制碾压密实检测高程及压实度报请监理检查验收土样送检、试验调配符合要求的土源控制回填土的含水量测量、控制监理检查验收 ①软基处理以就地取材为原则,事先备好干素土、石灰、砂石、片石等处理软基材料。
因工期较紧,采用水泥石灰土(含灰量分别为3%、10%)换填40~80cm的方法处理软基中湿略潮路基采用晾晒、换填、掺灰(一般为10%灰土)等加固措施处理,待路基强度与稳定性达到设计要求时,方进行下一步施工,处理深度根据实际情况确定清除建筑垃圾及拆除障碍物:路基土原地面以下的墓穴、井洞、根、管沟等障碍物必须清除,拆除障碍物后所留下的坑穴孔洞用合适的材料回填至周围标高,并压实到相邻面同等的密实度,用压路机将清理出的路基压实,用环刀法测检②路床成型:A、填方、挖方完工后,恢复道路中心桩,放出车行道边线为了保证路床结构整体性,路床宽度包括侧石的灰土宽度并在不受施工影响的位置引测辅助基线,设平面控制桩,以备施工过程中及时补桩B、路床大面积开挖采用机械开挖,小面积采用人工开挖为了防止机械超挖预留20cm左右让人工清挖弃土及时清运,不得乱堆乱放C、开挖至路床顶面时注意预留碾压沉降高度,其数值通过试验确定,一般碾压沉降高度控制在3cm左右D、路床碾压采用压路机碾压,碾压工作自边向中进行,遵循先轻后重、先稳后振、先慢后快以及轮迹重叠等原则碾压至表面无显著轮迹、达到要求压实度为止道路边缘、检查井、雨水口周围以及其他压路机碾压不到的地方,采用机夯或人力夯夯实,必须防止漏夯,并要求夯击面积重叠1/4~1/3。
E、碾压完成后,立即测定其含水量和湿密度,计算干密度和压实度,判断是否达到压实度标准压实度不合格处必须处理至合格,并按设计要求检测路床宽度、标高和平整度,根据检测结果进行整修5)水泥石灰土底基层的施工①工艺流程:见附图施工准备选做试验段调整配合比倒土、摊铺初碾、整型石灰摊铺灰土拌合机拌合水泥石灰土底基层施工工艺流程框图复检路床高程测量放样、人工清扫初碾、整型水泥摊铺灰土拌合机拌合复检数据收集、论证监理工程师确认测定、控制含水量监理工程师检查认可监理工程师检查认可原材送检、试验监理检查确认配合比混合料拌制运至现场测量路拱高程严格控制灰土含水量高度、密实度检查养生(限制通行)严格控制灰土含水量②施工要求:检查下承层的平整度和压实度:用15T三轮压路机进行碾压检验(压3~4遍),在碾压过程中如发。